KEY SUCCESS FACTORS:
- Maximum local content achievable for modules, temporary refuges,
local equipment rooms, process and utilities buildings
- First local Contractor to be awarded a multidisciplinary EPC Contract for offshore applications (highest quality standard required in the Oil & Gas Industry)
- Project delivered on time and without any punch list
- The complete project cycle is managed by internal resources (from feasibility studies and cost/performance optimization to the design of structures, electrical HVAC and safety systems, procurement, construction, assembly pre-commissioning, start-up, commissioning, load out activities and on site supervision/installation)
- Facilities located in a strategic position (Atyrau) and designed for all modular solutions
Project goal:
- Procurement and Fabrication of Offshore Buildings -In Country
Production capacity:
Place of project implementation:
Timeline:
- Oct 2009 — Dec 2011 (27 Months)
Client:
The SoW includes:
- Fabrication of steel structures for offshore modular buildings, local equipment rooms, superstructure for metal buildings, etc
Structural steel portion amounted to 3000 tonnes.